### Importance of operational risk management for ministry of finance treasury operations
- Ministry of finance manages very substantial government assets and liabilities and many large value transactions; large sums mean any risk exposure can have damaging financial consequences on the budget out-turn and the overall government balance sheet.
- Operational errors or failures can cause severe reputational and political damage reflecting on the competence of the ministry of finance covering treasury operations.
- Awareness of operational risk is low in many countries; very few ministries of finance have a business continuity and disaster recovery plan (BCP/DRP).
- Common causes of low attention to BCP/DRP:
  - perceived as private-sector only
  - not seen as priority
  - inadequate resources for an operational risk management (ORM) framework including BCP/DRP
  - responsibility delegated to information technology
  - treated as a one-off project rather than integral to day-to-day treasury operations
  - management neglect with the belief “it won’t happen to me”

### Types of risks faced by treasury
- Financial risks: market, liquidity, and credit risks—traditionally managed by a risk management unit in the ministry of finance.
- Business risks: new legislation, change of government, macro-economic performance, and other environmental factors—often managed as part of the budget planning process.
- Operational risks: loss of key personnel, settlement failure, compliance failure, theft, systems failure, building damage—managed via audit, recruitment policies, system controls, and business continuity planning.
- Operational risk is mainly endogenous to the ministry of finance (aside from external events such as natural catastrophes); linked to business environment, nature and complexity of treasury operations, processes and systems, and quality of management and information flows.
- There is normally no regulatory pressure to maintain a BCP/DRP for ministries of finance as exists for central banks.

### Technical Note objectives (TNM)
- What is operational risk management and its application to treasury operations.
- What is business continuity and disaster recovery planning and why it is important for treasury operations.
- How to develop and implement a business continuity and disaster recovery plan using a six practical-step process and how to have it imbedded into day-to-day treasury operations.
- What is needed to activate and what are the key procedures when activating the disaster recovery plan.

### Definition of operational risk and governance responsibilities
- Operational risk (Basel II definition): “the risk of loss resulting from inadequate or failed internal processes, people and systems or from external events.” The definition explicitly includes legal risk, but excludes strategic and reputation risk.
- Governing principles from Basel Committee on Banking Supervision and COSO, and elaborations by entities such as TransConstellation, can be applied to treasury operations.
- Treasurer responsibilities:
  - Be aware of major aspects of operational risks and approve and periodically review the ORM framework.
  - Ensure the framework defines operational risk and principles for identification, assessment, monitoring, and control/mitigation.
  - Consider a risk committee to oversee the framework.
- Senior management responsibilities:
  - Implement the ORM framework consistently throughout all treasury operations.
  - Ensure all staff understand their ORM responsibilities.
  - Develop policies, processes and procedures for managing operational risk across treasury activities.
  - Ensure operational risks of new activities, processes, and systems are assessed and managed before introduction.
  - Ensure regular monitoring of incidents that may cause business disruption and regular reporting to the treasurer and senior executives.
  - Ensure treasury has a business continuity and disaster recovery plan to maintain operations and limit losses in the event of disruption.
- Independent examination:
  - Use internal and/or external auditors to independently examine and assess the ORM framework and related policies, procedures and practices.

### Typical treasury operational risks
- Infrastructure and technology failures: computer systems, power, telecommunications, data and physical records.
- Incidents denying access to premises: inaccessibility or building damage.
- Dependencies on third party key service providers: central/commercial banks, telecom and internet providers, outsourced operations; resource failures from incidents such as a pandemic.
- Human errors or failures: lack of resources, skills, training, policies, procedures, delegations, code of conduct, and poor management.
- Failure to meet statutory, legal or contractual, human resources and other obligations including management objectives and reporting obligations.
- Natural and regional disasters: earthquake, tsunami, severe flooding, hurricane/typhoon, volcanic eruption, severe fires, landslides and civil disturbance or terrorism.

### Application and implementation of ORM in treasury operations
- ORM implementation can be evolutionary and incremental rather than perfect from the outset.
- Success factors:
  - Develop a culture of risk awareness across treasury and involve all staff.
  - Senior management must signal the importance of ORM and require staff participation.
  - Embed ORM principles into day-to-day operations and hold each line manager responsible for ORM in their business area.
- Role of a risk champion:
  - Appoint a “risk champion” to lead and guide ORM across treasury, coordinate reporting to the treasurer and senior management, and develop ORM policies, procedures and control environment.
  - Risk champion ideally has relevant background or experience; consider professional training in ORM and business continuity planning.
- Risk management unit and risk champion roles:
  - Drive development of the risk management process, monitor performance and execution, and report to the treasurer.
  - Act as advisers to senior managers in identifying risks and planning controls.

### Six-step process to develop and maintain an ORM framework
- Understand and document business activities.
- Identify, assess and measure risks.
- Develop risk management strategies.
- Implement risk management policies, limits and controls.
- Monitor performance and compliance with policies, limits and controls.
- Process for continuous improvement of the ORM framework.

### Considerations for service providers and assurance
- Service providers should demonstrate adequate controls and safeguards when hosting or processing data related to banking systems.
- Discuss use of International Standard on Assurance Engagements (ISAE) No.3402 with central and commercial banks.
- ISAE No.3402: service auditor’s examination represents an in-depth audit of a service organization’s control objectives and control activities, often including IT controls.
- Note: On June 15, 2011, ISAE No.3402 replaced SAS No.70.

### Case of Chile: Risk Management Process — objectives and core elements
- Main objective: “to have an efficient internal control system and to comply with a Risk Management process structured, consistent and coordinated for effective and efficient achievement of institutional goals and objectives”.
- Risk Management objectives:
  - Identify risks and opportunities
  - Analyze the risks in the process
  - Assessing risks
  - Set the risk treatment
  - Monitor and review (feedback)
  - Construction of the risk matrix

### Case of Chile: six-step risk management process
- Step 1: Risk Policy — define roles and responsibilities; determine key processes; communicate and publish consistent with Quality of Service Policy.
- Step 2: Survey Process — raise processes; identify risks by type.
- Step 3: Development of the Matrix — classify transverse processes; weight processes and sub-processes; identify risk type; justify strategic weighting.
- Step 4: Establish Ranking — ranking by process and sub-process.
- Step 5: Establish Treatment Plan — measures, timelines, responsibilities, potential impact (reduce, accept, avoid, sharing) and performance indicators, measurement period goal.
- Step 6: Monitoring and Review — generate reports, monitor, diagnose and propose improvements.

### Chile: Strategic Risk Matrix elements
- Matrix headings/elements: Information Processing; Critical Risk Information; Key Control; Process; Sub-process; Stage; Objective; Critical Risk; Probability; Impact; Severity; Control Design; Control Effectiveness; Risk Exposure.

### Business Continuity and Disaster Recovery Planning: purpose and scope
- Business continuity management/planning: development, implementation and maintenance of policies, frameworks and programs to assist treasury manage a business disruption and build treasury resilience.
- Business continuity planning assists in preventing, preparing for, responding to, managing, and recovering from impacts of an incident or disruptive event.
- Business continuity complements ORM by establishing cost-effective measures should an event occur; BCP/DRP deals with actual events.
- BCP/DRP should address operational risks where environmental factors or poor operational controls raise potential for loss or damage to treasury operations (people, information, infrastructure, premises).
- BCP/DRP concentrates on areas identified as having a combination of very-high/high probability and catastrophic/major impact and may also cover lower probability events that have catastrophic/major impact.

### Risk intervention strategies (treasury)
- prevention or avoidance (examples: installing back-up power generators, using more than one telecom provider, training staff, implementing fraud prevention policies and procedures)
- transference (take out insurance or outsourcing with BCP/DRP in service level agreements)
- containment (limit potential impact in early stages using controls or techniques; implement fraud detection policies and procedures; escalation procedures; more than one person to perform a task)
- acceptance and recovery (resume operations using the disaster recovery plan regularly tested at the recovery location (alternate site))

### Cost-recovery time trade-off
- Cost to shorten recovery time is non-linear; reducing recovery time to minutes rather than hours and days typically increases cost exponentially (example activities: replication of systems, mirroring of data, redundancy of communication and infrastructure, alternate site quickly activated).
- Recovery of treasury’s most critical activities, processes and systems are likely to be hours or for some activities 1-2 days; some end-of-day activities may require completion before day’s-end and manual processes may be more cost effective for those.

### Treasury policy for business continuity planning
- perform a business impact analysis, and develop mitigation strategies, which will ensure the continuity of its business, operations and technology components in the event the existing environment is unavailable;
- develop and maintain a comprehensive business continuity and disaster recovery plan (BCP/DRP) to ensure that essential/critical treasury activities are recoverable;
- business continuity planning and the BCP/DRP should be developed in accordance with international standards such as the Business Continuity Management standard BS-25999 or International Standards Organization ISO-27031; and
- report the status of business continuity planning and the BCP/DRP annually to the treasurer and senior management in the ministry of finance.

### BCP/DRP objectives for treasury
- protect government’s interests in terms of reputation, reporting and resource impact, and impact on treasury operations;
- ensure government meets all statutory, contractual and market obligations;
- ensure essential/critical activity disrupted by an incident or event is re-established within the designated recovery period using the DRP; and
- ensure BCP/DRP is integral to day-to-day operations with regular updates, training and testing.

### Six-step process to develop a BCP/DRP
- Step 1: Document business activities and critical processes and systems.
- Step 2: Undertake business impact analysis to assess probability and impact.
- Step 3: Develop BCP/DRP (include third parties).
- Step 4: Implement or update BCP/DRP.
- Step 5: Training to imbed into day-to-day operations of the treasury.
- Step 6: Regular (annual) testing and updating.

### Developing a BCP/DRP: key steps and tools
- Step 1: Document Business Activities
  - Use process maps, process-flow analysis, and existing procedure manuals.
  - Identify critical processes and systems and the time period when these are required (minutes, hours or days).
  - Maintain a table of essential/critical systems (example Table 1 columns: System; Time Period (minutes, hours or days); data Back-up (time and location); Access location (alternate site or data center)).
- Step 2: Business Impact Analysis
  - Convene workshops and brainstorming sessions across treasury functions.
  - Assess probability and impact separately using categories: Very-High / High / Medium / Low / Very Low Probability and Catastrophic / Major / Moderate / Minor / Insignificant Impact.
  - Consider three impact categories: Reputational impact; Reporting & resource impact; Impact on treasury operations.
  - Associate a probability and impact rating for each activity. Activities ranked 4 and 5 are identified for detailed mitigation; treasury may include rank 3 depending on risk tolerance.
  - Time criticality categorization examples: end-of-day, within 24 hours, 48 hours, 72 hours, 5 business days, or more than 5 business days.

### Incidents that may affect treasury operations (examples)
- Infrastructure and Technology Failures: Power failure, Hardware failure, Software failure, Data corruption including viruses, LAN/WAN/Intranet/Internet failure, Internal flood (sprinklers, pipes), Voice network failure, Theft of equipment, Theft of data/information, Poor maintenance, Accidental damage, Sabotage.
- Incidents where Access to Premises is denied: Flooding or a fire concern, Health and safety violation, Hazardous chemicals accident, Gas or chemical leak, Industrial action or riot, Bomb or terrorist threat, Building fire or explosion, Internal/external flood, Sabotage or terrorism.
- Key Service Providers or Resource Failures: Failure of key service providers (telephone, internet, banking etc), Third party providers (Central Bank and other outsourced operations), Impact of incident on critical teams or groups (pandemic, travel, group incident).
- Staff, Management and Related human Failures: Human error, Poor training or inadequate supervision, Failure to follow code of conduct, Lack of policy guidance, Poor understanding of risk environment, Poorly specified delegations, Failure to follow administrative practices, Key person risk, Fraudulent, corrupt or dishonest practices.
- Failure to Meet Statutory, legal, human Resources and Other Obligations: Legal/statutory obligations, Management directives, Procedures manuals and delegated authorities, Reporting obligations, Contractual obligations, Health and safety regulations.
- Major natural and Regional disasters: Major earthquake, Hurricane, cyclone or tornado, Tsunami, Volcanic eruption, Severe fires, Civil disturbance, Severe flooding, Landslides, Terrorism.

### Impact assessment criteria (examples and categories)
- Assessment levels with reporting and resource implications:
  - Catastrophic: Reported to President or Congress; Significant amount of time spent dealing with impact (i.e. greater than 20 person-days).
  - Major: Reported to Minister; Large amount of time spent dealing with impact (i.e. between 10 and 20 person-days).
  - Moderate: Reported to the entity responsible for monitoring treasury; Moderate amount of time spent dealing with impact (i.e. between 5 and 10 person-days).
  - Minor: Included in internal treasury reports; Some amount of time spent dealing with impact (i.e. less than 5 person-days).
  - Insignificant: No reports needed; Minimal amount of time spent dealing with impact (i.e. less than 5 person-hours).

### Risk/Impact matrix (Table 4)
- Matrix cell values for Impact Level of Risk (Insignificant, Minor, Moderate, Major, Catastrophic) vs Likelihood Level of Risk (Very High, High, Medium, Low, Very Low):
  - Very High: 3 4 4 5 5
  - High: 2 3 4 4 5
  - Medium: 2 2 3 4 4
  - Low: 1 2 2 3 4
  - Very Low: 1 1 2 2 3
- Strategies should focus on incidents/events ranked 4 and 5.

### Step 3: Develop BCP/DRP (post-impact analysis)
- Develop strategies focused on incidents/events ranked 4 and 5 in Table 4.
- Select cost-effective risk treatment(s): prevention, transference, containment, acceptance & recovery.
- Submit a business continuity planning report to senior management summarizing greatest risks, mitigation techniques, recommended actions including activation of DRP, and an estimate of costs.
- DRP facilitates:
  - smooth transition to recovery operations following a major incident;
  - escalation of recovery operations for prolonged disruption;
  - return to normal operations as quickly as possible.
- DRP includes incident management and recovery team structure, administration and IT support (example command center structure provided).

### Step 4: Implement the BCP/DRP
- Risk champion or risk management unit to oversee implementation and integrate BCP/DRP into ORM monitoring and control policies and procedures.
- Raise awareness with external parties about their roles during activation of DRP.
- Require third party providers to include BCP/DRP in service level agreements or memorandum of understanding (examples: central bank, telecommunications, banking, external IT providers).
- Integrate BCP/DRP with other critical systems such as IFMIS and debt recording and management system.

### Step 5: Training
- Training components and modalities:
  - awareness presentations for existing employees (and possibly as part of orientation/induction for new employees)
  - provision of a training manual
  - interactive training (Intranet)
- Use of alternate site for training and testing to reduce key person risk and broaden staff capabilities.
- Consider stationing staff at alternate site or rotating staff to ensure familiarity and continuity.

### Step 6: Regular testing and updating
- Critical systems and processes should be tested annually and the BCP/DRP updated based on test results and continual improvement.
- Individual system/process testing recommended; full-plan testing is resource-intensive and may only be appropriate at weekends.
- Testing types and frequencies (Table 5: DRP timeframe for maintenance and testing):
  - BCP/DRP documentation review and update: six monthly
  - Technology recovery testing: six monthly
  - Staff familiarity testing: annually
  - Scenario (white board) testing: annually
  - Full test (simulated incident): annually
- Ongoing monitoring is the responsibility of line managers with coordinating responsibility assigned to the risk champion or risk management unit.
- Revisit the six-step process on an annual basis; report new business activities and changes to procedures/systems to the risk champion or risk management unit during planning; include business continuity risks in business cases and project budgets.

### Activating the Disaster Recovery Plan: command center and roles
- Command center primary role: coordination, control and exchange of information across treasury; initiate decision-making for problems and major incidents; manage communications with external parties.
- Command center members and associated groups include ministry of finance senior management and the treasurer; representative(s) from business systems/IT; representatives from support services such as HR, administration and/or building services.
- Command center responsibilities:
  - central point of contact for recovery operations for staff, suppliers, and media
  - collect and collate information on status and progress of recovery
  - distribute instructions to staff, counterparties and other affected third parties
  - quickly decide to invoke recovery activities based on available information
  - coordinate communications with ministry of finance and manage communications with the media
  - maintain the flow of information to staff, counterparties and other key stakeholders
  - approve significant expenditure associated with the recovery
  - monitor compliance requirements throughout the recovery process
  - ensure effective security in recovery locations
  - determine escalation of recovery activities for significant incidents
  - plan and manage restoration and recommissioning of the treasury primary site
- Business systems responsibilities during recovery:
  - restoration of e-mail, internet and other essential communication services
  - restoration or rerouting of electronic payment or banking systems with central bank and commercial banks
  - retrieval of back-up data and restoration of data to resume critical functions at the recovery location

### Case of UK DMO – Business Recovery Management: objectives and steps
- Objectives:
  - Supplement Incident Management Plan to ensure individual business operations are recovered effectively and timely.
  - Business Recovery Management is used in conjunction with the Impact Analysis component of the BCP.
- Business Recovery Steps:
  - Step 1: Business Assessment — establish current status of each business activity; confirm IT system and resource availability; assess market conditions; establish status of key stakeholders.
  - Step 2: Status Report — provide status reports including high priority activities, suspended activities, unavailable systems, resource requirements and feedback; additional recovery actions may include procurement and deployment of equipment, third party liaison, technology project management, cut-over and decommissioning.
  - Step 3: Prioritization — managers determine priorities; Senior Managers confirm priorities and communicate them; IT informed of system requirements.
  - Step 4: Decision-making — strategic decisions referred to appropriate forums; document decisions on suspending or cancelling operations.
  - Step 5: Implementation — teams implement agreed activities using manual workarounds; staff report progress; stakeholder statements issued as needed.
  - Step 6: Returning to Main Office Location — building clearance; validation testing; detailed migration plan by IT; Senior Management communication strategy for remigration.

### UK DMO: support services, emergency response, and objectives
- Support services (HR, administration, building services) expected to:
  - track staff whereabouts and ensure safety/welfare
  - answer phones and relay messages
  - contact staff to confirm availability
  - arrange catering, accommodation, trauma counseling, emergency payments, child care, staff rotation
  - ensure security at incident and temporary recovery locations
  - facilitate insurance claims and emergency purchasing; redirect mail and couriers
- Emergency Response phases:
  - Evacuation and Containment
  - Damage Assessment
  - Recovery Decision
- Objective and time targets:
  - Primary objective: re-establishing critical activities within 24 hours (or if needed by the end-of-day)
  - Other essential activities: within 48-72 hours
- Staff communication: provide staff with an information sheet and important contact details; make information available in formats storable on mobile devices.

### Business Recovery (post decision) — sequence
- Activate Recovery Infrastructure:
  - invoke BCP for systems and communications; inbound calls diverted; key production systems revert to alternate site; data accessed at alternate site or data center; staff may relocate to third party premises for designated systems.
- Survival Level Operations:
  - limit activities to core functions initially; less time-critical functions suspended or staff directed to work from home.
- Escalation:
  - if away from primary site generally exceeds two weeks, escalate business activity with predetermined escalation priorities and indicative timeframes.
- Primary Site Recommissioning:
  - salvage, restore or replace damaged or lost property, facilities and services and recommence business at the primary site.

### Post Incident Review
- Conduct comprehensive review to update/improve recovery plan and infrastructure based on incident experience.
- Examine each six-step process to identify weaknesses/omissions and revise the BCP/DRP.
- Potential outcomes: changes to business processes; underlying infrastructure including systems and facilities at the alternate site; enhanced training and testing; other identified changes.

### Conclusion and key recommendations
- An ORM framework including a BCP/DRP should be a priority for any treasury given operational risks and critical functions performed.
- The development of a BCP/DRP should be an integral part of day-to-day treasury operations, not a one-off project.
- Follow the six-step processes to develop, implement, test and maintain ORM and BCP/DRP to ensure ongoing treasury resilience.

*Source: Technical Notes and Manuals 11/05 | 2011*

### InTROduCTIOn

### InTROduCTIOn

### Importance of operational risk management for ministry of finance treasury operations
- Ministry of finance bears responsibility for management of very substantial government assets and liabilities and for many large value transactions; large sums mean any risk exposure can have damaging financial consequences on the budget out-turn and the overall government balance sheet.
- Operational errors or failures can cause severe reputational and political damage reflecting on the competence of the ministry of finance covering treasury operations.
- Awareness of operational risk is low in many countries; very few ministries of finance have a business continuity and disaster recovery plan (BCP/DRP).
- Common causes of low attention to BCP/DRP: perceived as private-sector only, not seen as priority, inadequate resources for an operational risk management (ORM) framework including BCP/DRP, responsibility delegated to information technology, treated as a one-off project rather than integral to day-to-day treasury operations, and management neglect with the belief “it won’t happen to me”.

### Types of risks faced by treasury
- Financial risks: traditionally managed by a risk management unit located in the ministry of finance that includes market, liquidity, and credit risks.
- Business risks: such as new legislation, change of government, macro-economic performance and any other factors affecting the ministry of finance’s environment—often managed as part of the budget planning process.
- Operational risks: a range of threats from loss of key personnel, settlement failure, and compliance failure, to theft, systems failure and building damage—operational risk management aims to ensure the integrity and quality of the operations of ministry of finance and treasury using tools including audit, recruitment policies, system controls, and business continuity planning.
- Operational risk is mainly endogenous to the ministry of finance (aside from external events such as natural catastrophes); it is linked to the business environment, nature and complexity of treasury operations, processes and systems in place, and quality of management and information flows.
- There is normally no regulatory pressure to put in place adequate measures to monitor and control operational risks and maintain a BCP/DRP as is the case with central banks.

### Technical Note objectives (TNM)
- This technical note and manual (TNM) addresses the following main issues:
  - What is operational risk management and how this should be applied to treasury operations.
  - What is business continuity and disaster recovery planning and why it is important for treasury operations.
  - How to develop and implement a business continuity and disaster recovery plan using a six practical-step process and how to have it imbedded into the day-to-day operations of the treasury.
  - What is needed to activate and what are the key procedures when activating the disaster recovery plan.

### Definition of operational risk and governance responsibilities
- Operational risk (Basel II definition): “the risk of loss resulting from inadequate or failed internal processes, people and systems or from external events.” The definition explicitly includes legal risk, but excludes strategic and reputation risk.
- The governing principles from Basel Committee on Banking Supervision and COSO, and elaborations by entities such as TransConstellation, though primarily designed for banking and financial sector, can be applied to treasury operations.
- The treasurer should:
  - Be aware of major aspects of operational risks as a distinct risk category and approve and periodically review the operational risk management framework applicable to treasury.
  - Ensure the framework provides a definition of operational risk and lays down principles for identification, assessment, monitoring, and control/mitigation of operational risks.
  - Consider a risk committee to oversee the framework.
- Senior management responsibilities:
  - Implement the ORM framework consistently throughout all treasury operations.
  - Ensure all staff understand their ORM responsibilities.
  - Develop policies, processes and procedures for managing operational risk across treasury activities, processes and systems.
  - Ensure operational risks of new activities, processes, and systems are adequately assessed and managed before introduction.
  - Ensure regular monitoring of incidents that may cause business disruption and regular reporting to the treasurer and senior executives.
  - Ensure treasury has a business continuity and disaster recovery plan to maintain operations and limit losses in the event of disruption.
- Independent examination:
  - Once the ORM framework is established, treasury should consider using internal and/or external auditors to independently examine and assess the framework and related policies, procedures and practices.

### Typical treasury operational risks (Box 1)
- Infrastructure and technology failures covering computer systems, power, telecommunications, data and physical records.
- Incidents where access to premises is denied, either through inaccessibility or building damage.
- Dependencies on third party key service providers such as the central and/or commercial banks, telecom and internet providers, and other outsourced operations, or resource failures from such incidents as a pandemic.
- Human errors or failures through lack of resources, skills, training, policies, procedures, delegations, code of conduct, and poor management.
- Failure to meet statutory, legal or contractual, human resources and other obligations including management objectives and reporting obligations.
- Natural and regional disasters covering incidents such as earthquake, tsunami, severe flooding, hurricane/typhoon, volcanic eruption, severe fires, landslides and civil disturbance or terrorism.

### Application and implementation of ORM in treasury operations
- ORM is a wide umbrella; implementation can be evolutionary and incremental rather than perfect from the outset.
- Success factors:
  - Develop a culture of risk awareness across treasury and ensure all staff are involved in developing and implementing the framework.
  - Senior management must signal importance of ORM and require staff participation and ongoing cooperation.
  - Embed ORM principles into day-to-day operations; make each line manager responsible for ORM in their business area.
- Role of a risk champion:
  - Appoint a “risk champion” to take overall responsibility for ORM: lead and guide the process across treasury, coordinate reporting to the treasurer and senior management, and develop ORM policies, procedures and control environment.
  - The risk champion ideally has relevant background or experience; professional training opportunities in ORM and business continuity planning could be considered.
- The risk management unit and risk champion have two roles:
  - Drive development of the risk management process, monitor performance and execution, and report to the treasurer.
  - Act as advisers to senior managers in identifying risks and planning controls.

### Six-step process to develop and maintain an ORM framework
- The development and maintenance of an ORM framework for treasury should follow a six-step process:
  - understand and document business activities
  - identify, assess and measure risks
  - develop risk management strategies
  - implement risk management policies, limits and controls
  - monitor performance and compliance with policies, limits and controls
  - process for continuous improvement of the ORM framework

### Considerations for service providers and assurance
- Service providers such as the central bank and commercial banks should demonstrate adequate controls and safeguards when they host or process data related to banking systems.
- Treasury should discuss with central and commercial banks the use of International Standard on Assurance Engagements (ISAE) No.3402, Assurance Reports on Controls at a Service Organization, as a widely recognized auditing standard developed by the International Auditing and Assurance Standards Board (IAASB).
- A service auditor’s examination performed in accordance with ISAE No.3402 represents that a service organization has been through an in-depth audit of its control objectives and control activities, often including controls over information technology and related processes.
- Note: On June 15, 2011, ISAE No.3402 replaced the Statement on Auditing Standards (SAS) No.70, Service Organizations developed by the American Institute of Certified Public Accountants (AICPA).

*Technical Notes and Manuals 11/05  |  2011*

### Box 2: Case of Chile: Outline of the Risk Management Process

### Box 2: Case of Chile: Outline of the Risk Management Process

### Risk Management: objective and core elements
- Main objective: “to have an efficient internal control system and to comply with a Risk Management process structured, consistent and coordinated for effective and efficient achievement of institutional goals and objectives”.
- Risk Management has the following objectives:
  - Identify risks and opportunities
  - Analyze the risks in the process
  - Assessing risks
  - Set the risk treatment
  - Monitor and review (feedback)
  - Construction of the risk matrix

### Risk Management: six-step process (Chile)
- Step 1: Risk Policy
  - Define roles and responsibilities of the process of risk management
  - Determine the key processes involved in improving the quality of service
  - Be communicated, published and consistent with the Quality of Service Policy
- Step 2: Survey Process
  - Raise the processes developed by the Quality of Service Policy
  - Identify risks by type
- Step 3: Development of the Matrix
  - Classification of transverse processes
  - Process and sub-process weights
  - Risk type
  - Justification of strategic weighting
- Step 4: Establish Ranking
  - Ranking by the process set
  - Establish ranking by sub-process
- Step 5: Establish Treatment Plan
  - Measures, timelines, responsibilities, potential impact (reduce, accept, avoid, sharing) and performance indicators, measurement period goal
- Step 6: Monitoring and Review
  - Generating reports
  - Monitoring
  - Diagnosis and improvement proposals

### Strategic Risk Matrix (structure and elements)
- Matrix headings and elements as presented:
  - Information Processing
  - Critical Risk Information
  - Key Control
  - Process
  - Sub-process
  - Stage
  - Objective
  - Critical Risk
  - Probability
  - Impact
  - Severity
  - Control Design
  - Control Effectiveness
  - Risk Exposure

### Business Continuity and Disaster Recovery Planning: purpose and scope
- Business continuity management or planning defined as the development, implementation and maintenance of policies, frameworks and programs to assist treasury manage a business disruption, and build treasury resilience.
- Business continuity planning assists in preventing, preparing for, responding to, managing, and recovering from the impacts of an incident or disruptive event.
- Business continuity is that part of ORM that establishes cost-effective measures should an event occur; it deals with actual events and complements overall ORM which focuses on possibility and proactive management.
- BCP/DRP should address operational risks where environmental factors or poor operational controls raise potential for loss or damage to treasury operations (people, information, infrastructure, premises).
- BCP/DRP concentrates on areas identified as having a combination of very-high/high probability and catastrophic/major impact and may also cover lower probability events that have catastrophic/major impact.

### Risk intervention strategies (treasury)
- prevention or avoidance (examples: installing back-up power generators, using more than one telecom provider, training staff, implementing fraud prevention policies and procedures)
- transference (take out insurance or outsourcing with BCP/DRP in service level agreements)
- containment (limit potential impact in early stages using controls or techniques; implement fraud detection policies and procedures; escalation procedures; more than one person to perform a task)
- acceptance and recovery (resume operations using the disaster recovery plan regularly tested at the recovery location (alternate site))

### Cost-recovery time trade-off
- The cost to shorten recovery time is non-linear; reducing recovery time to minutes rather than hours and days typically increases cost exponentially (example activities: replication of systems, mirroring of data, redundancy of communication and infrastructure, alternate site quickly activated).
- Recovery of treasury’s most critical activities, processes and systems are likely to be hours or for some activities 1-2 days; some end-of-day activities may require completion before day’s-end and manual processes may be more cost effective for those.

### Treasury policy for business continuity planning
- perform a business impact analysis, and develop mitigation strategies, which will ensure the continuity of its business, operations and technology components in the event the existing environment is unavailable;
- develop and maintain a comprehensive business continuity and disaster recovery plan (BCP/DRP) to ensure that essential/critical treasury activities are recoverable;
- business continuity planning and the BCP/DRP should be developed in accordance with international standards such as the Business Continuity Management standard BS-25999 or International Standards Organization ISO-27031; and
- report the status of business continuity planning and the BCP/DRP annually to the treasurer and senior management in the ministry of finance.

### BCP/DRP objectives for treasury
- government’s interests are protected in terms of reputation, reporting and resource impact, and impact on treasury operations;
- government meets all statutory, contractual and market obligations;
- should an essential/critical activity be disrupted by an incident or event, this activity is re-established within the designated recovery period using the DRP; and
- BCP/DRP is an integral part of treasury’s day-to-day operations and that it is regularly updated with ongoing staff training and testing.

### Six-step process to develop a BCP/DRP
- Step 1: Document business activities and critical processes and systems
- Step 2: Undertake business impact analysis to assess probability and impact
- Step 3: Develop BCP/DRP (include third parties)
- Step 4: Implement or update BCP/DRP
- Step 5: Training to imbed into the day-to-day operations of the treasury
- Step 6: Regular (annual) testing and updating

### Developing a BCP/DRP: key steps and tools
- Step 1: Document Business Activities
  - Use process maps, process-flow analysis, and existing procedure manuals.
  - Identify critical processes and systems and the time period when these are required (minutes, hours or days).
  - Maintain a table of essential/critical systems (example Table 1 columns: System; Time Period (minutes, hours or days); data Back-up (time and location); Access location (alternate site or data center)).
- Step 2: Business Impact Analysis
  - Convene workshops and brainstorming sessions across treasury functions.
  - Assess probability and impact separately (example categories: Very-High / High / Medium / Low / Very Low Probability and Catastrophic / Major / Moderate / Minor / Insignificant Impact) from reputational, reporting & resource, and impact on treasury operations perspectives.
  - Consider three impact categories:
    - Reputational impact
    - Reporting & resource impact
    - Impact on treasury operations
  - Associate a probability and impact rating for each activity. Activities ranked 4 and 5 are identified for detailed mitigation; treasury may include rank 3 depending on risk tolerance.
  - Time criticality categorization examples: end-of-day, within 24 hours, 48 hours, 72 hours, 5 business days, or more than 5 business days.

### Incidents that may affect treasury operations (examples from Table 2)
- Infrastructure and Technology Failures: Power failure, Hardware failure, Software failure, Data corruption including viruses, LAN/WAN/Intranet/Internet failure, Internal flood (sprinklers, pipes), Voice network failure, Theft of equipment, Theft of data/information, Poor maintenance, Accidental damage, Sabotage.
- Incidents where Access to Premises is denied: Flooding or a fire concern, Health and safety violation, Hazardous chemicals accident, Gas or chemical leak, Industrial action or riot, Bomb or terrorist threat, Building fire or explosion, Internal/external flood, Sabotage or terrorism.
- Key Service Providers or Resource Failures dependencies: Failure of key service providers (telephone, internet, banking etc), Third party providers (Central Bank and other outsourced operations), Impact of incident on critical teams or groups (pandemic, travel, group incident).
- Staff, Management and Related human Failures: Human error, Poor training or inadequate supervision, Failure to follow code of conduct, Lack of policy guidance, Poor understanding of risk environment, Poorly specified delegations, Failure to follow administrative practices, Key person risk, Fraudulent, corrupt or dishonest practices.
- Failure to Meet Statutory, legal, human Resources and Other Obligations: Legal/statutory obligations, Management directives, Procedures manuals and delegated authorities, Reporting obligations, Contractual obligations, Health and safety regulations.
- Major natural and Regional disasters: Major earthquake, Hurricane, cyclone or tornado, Tsunami, Volcanic eruption, Severe fires, Civil disturbance, Severe flooding, Landslides, Terrorism.

### Impact assessment criteria (examples and categories)
- Example impact assessment framework (Table 3) uses assessment levels and describes impacts for Reputational Impact; Reporting & Resource Impact; Impact on Treasury Operations across the ratings: Catastrophic, Major, Moderate, Minor, Insignificant.
- Illustrative time and resource impacts:
  - Catastrophic: Reported to President or Congress; Significant amount of time spent dealing with impact (i.e. greater than 20 person-days).
  - Major: Reported to Minister; Large amount of time spent dealing with impact (i.e. between 10 and 20 person-days).
  - Moderate: Reported to the entity responsible for monitoring treasury; Moderate amount of time spent dealing with impact (i.e. between 5 and 10 person-days).
  - Minor: Included in internal treasury reports; Some amount of time spent dealing with impact (i.e. less than 5 person-days).
  - Insignificant: No reports needed; Minimal amount of time spent dealing with impact (i.e. less than 5 person-hours).

### Risk/Impact matrix (Table 4)
- Matrix layout: Impact Level of Risk (Insignificant, Minor, Moderate, Major, Catastrophic) vs Likelihood Level of Risk (Very High, High, Medium, Low, Very Low) with the following cell values:
  - Very High: 3 4 4 5 5
  - High: 2 3 4 4 5
  - Medium: 2 2 3 4 4
  - Low: 1 2 2 3 4
  - Very Low: 1 1 2 2 3

### Step 3: Develop BCP/DRP (post-impact analysis)
- Develop strategies focused on incidents/events ranked 4 and 5 in Table 4.
- Select cost-effective risk treatment(s) (prevention, transference, containment, acceptance & recovery).
- Submit a business continuity planning report to senior management summarizing greatest risks, mitigation techniques, recommended actions including activation of DRP, and an estimate of costs for senior management to assess cost-risk trade-off.
- DRP documents the recovery component and facilitates:
  - smooth transition to recovery operations following a major incident;
  - escalation of recovery operations for prolonged disruption;
  - return to normal operations as quickly as possible.
- DRP includes incident management and recovery team structure, administration and IT support (example command center structure provided).

### Step 4: Implement the BCP/DRP
- Risk champion or risk management unit to oversee implementation and integrate BCP/DRP into ORM monitoring and control policies and procedures.
- Raise awareness with external parties so they understand their roles during activation of DRP.
- Require third party providers to have BCP/DRP included in service level agreements or memorandum of understanding (examples: central bank, telecommunications, banking, external IT providers).
- Integrate BCP/DRP with other critical systems such as IFMIS and debt recording and management system.

### Step 5: Training
- Training components and modalities:
  - awareness presentations for existing employees (and possibly as part of orientation/induction for new employees)
  - provision of a training manual
  - interactive training (Intranet)
- Use of alternate site for training and testing to reduce key person risk and broaden staff capabilities.
- Consider stationing staff at alternate site or rotating staff to ensure familiarity and continuity.

### Step 6: Regular testing and updating
- Critical systems and processes should be tested annually and the BCP/DRP updated based on test results and continual improvement.
- Individual system/process testing recommended; full-plan testing is resource-intensive and may only be appropriate at weekends.
- Testing types and frequencies (Table 5: DRP timeframe for maintenance and testing):
  - BCP/DRP documentation review and update: six monthly
  - Technology recovery testing: six monthly
  - Staff familiarity testing: annually
  - Scenario (white board) testing: annually
  - Full test (simulated incident): annually
- Ongoing monitoring is the responsibility of line managers with coordinating responsibility assigned to the risk champion or risk management unit.
- Revisit the six-step process on an annual basis; report new business activities and changes to procedures/systems to the risk champion or risk management unit during planning; include business continuity risks in business cases and project budgets.

### Activating the Disaster Recovery Plan: command center and roles
- Command center primary role: coordination, control and exchange of information across treasury; initiate decision-making for problems and major incidents; manage communications with external parties.
- Command center members and associated groups include:
  - ministry of finance senior management and the treasurer
  - representative(s) from business systems/IT
  - representatives from support services such as HR, administration and/or building services
- Command center responsibilities:
  - provide a central point of contact for recovery operations for staff, suppliers, and media
  - facilitate collection and collation of information on status and progress of recovery
  - facilitate distribution of instructions to staff, counterparties and other affected third parties
  - quickly make the decision to invoke recovery activities based on available information
  - coordinate communications with ministry of finance
  - manage communications with the media either directly or through a media liaison person
  - maintain the flow of information to staff, counterparties and other key stakeholders
  - approve significant expenditure associated with the recovery
  - monitor compliance requirements throughout the recovery process
  - ensure that effective security is maintained in recovery locations
  - determine how the scope of recovery activities will be escalated for significant incidents
  - plan and manage restoration and recommissioning of the treasury primary site
- Business systems responsibilities during recovery:
  - restoration of e-mail, internet and other essential communication services
  - restoration or rerouting of electronic payment or banking systems with central bank and commercial banks
  - retrieval of back-up data and restoration of data to resume critical functions at the recovery location

*Source: Box 2: Case of Chile: Outline of the Risk Management Process (Technical Notes and Manuals 11/05 | 2011).*

### Box 3: Case of UK DMO – Business Recovery Management

### Box 3: Case of UK DMO – Business Recovery Management

### Objectives
- Business Recovery Management supplements the Incident Management Plan to ensure individual business operations are recovered in an effective and timely manner.
- Business Recovery Management is used in conjunction with the Impact Analysis component of the BCP.
  - Impact Analysis provides a status report of how an incident may affect certain critical functions and provides actions and workarounds for specific critical processes.
  - Business Recovery Management looks at how the business operations are recovered following the incident and is used to assess and determine approaches to restoring key business operations.

### Business Recovery Steps
- Step 1: Business Assessment (Managers and/or Team Leaders)
  - Establish the current status of each business activity
  - Confirm IT system and resource availability for each business activity
  - Assess market conditions following any widespread incident
  - Establish status of key stakeholders
- Step 2: Status Report (Managers and/or Team Leaders)
  - Provide status reports to senior management for each business area including:
    - High priority activities to be completed
    - Activities that will be suspended
    - Systems that are currently unavailable
    - Resource requirements and availability
    - Feedback from stakeholders
  - Additional recovery actions may include:
    - procurement, configuration and deployment of additional user workstations, peripheral equipment, network and cabling capacity, phone lines and handsets
    - procurement, configuration and deployment of additional server equipment and telephony services to support the escalation of recovery activities when recommissioning of the treasury primary site is likely to take more than, say, two weeks
    - third party liaison to provide user support
    - technology project management of the restoration and recommissioning of the treasury primary site
    - cut-over to normal operations and decommissioning of temporary services
- Step 3: Prioritization
  - Management responsible for each business area to determine the order of priorities for their respective areas
  - Senior Managers to confirm priorities of key business operations and communicate to Managers and Team Leaders
  - IT to be made aware of system requirements based on business priorities
- Step 4: Decision-making
  - Any strategic decisions referred to appropriate forums
  - Decisions on whether to suspend or cancel any specific operations
  - Decisions should be documented and reported to relevant business areas
- Step 5: Implementation
  - Individual teams to implement agreed business activities using any manual workarounds as identified in the Impact Analysis
  - Staff to report progress and completion of activities to management so that subsequent assessments and prioritizations can be made
  - Any statements to stakeholders made in respect of any revised or suspended activities
- Step 6: Returning to Main Office Location
  - Once the building manager has given clearance for reoccupation of main office location and the systems & telecommunications infrastructure have been restored, the remigration will require:
    - Validation that the infrastructure has been restored through testing by business areas, coordinated by Team Leaders
    - A detailed plan of migration to be prepared by the IT management team including synchronizing and testing the cutting back of systems and re-setting the disaster recovery site–the detail of this will depend on the nature and impact of the original incident
    - Senior Management Group should meet and agree a communication strategy involving an announcement to the market and advising key contacts of the remigration

### Support services (HR, administration and building services staff)
- Support services will be expected to report to the command center team and provide assistance as directed. This may include:
  - tracking staff whereabouts and ensuring staff safety and welfare
  - answering the phones and relaying messages
  - contacting staff to relay messages and confirm availability
  - arranging catering, accommodation, trauma counseling, emergency payments, organisation of child care, staff rotation etc
  - ensuring security is enforced at the incident and any temporary recovery location
  - facilitation of insurance claims and emergency purchasing
  - redirection of mail and couriers

### Emergency Response
- Emergency response phases following an incident or event:
  - Evacuation and Containment: actions by emergency response personnel to contain the incident, assure the safety of staff, prevent further damage or loss and ensure the treasury primary site is secure
  - Damage Assessment: members of the command center team (including business systems and support services) evaluate the magnitude of the incident or event and decide upon a course of action and/or recovery
  - Recovery Decision: based on the damage assessment, a decision is made regarding how and where to recover essential/critical business functions. If the incident or event can be isolated and contained, actions are taken to restore treasury operations using standard operating policies and procedures. Staff must be made aware of their role during a recovery operation and recovery information must be clearly and regularly delivered to staff; staff will either return home until they hear otherwise or relocate to the alternate site
- Objective and time targets:
  - The objective for the emergency response is to minimize the risk to treasury’s business activities and operations in the primary site.
  - Primary objective: re-establishing critical activities within 24 hours (or if needed by the end-of-day)
  - Other essential activities: within 48-72 hours
- Staff communication:
  - Each staff member should be issued with an information sheet and important contact details (treasury, ministry of finance and central bank), including existing mobile and home telephone numbers, external contact details, and treasury key contacts.
  - This information can be made available in a format that can be stored on treasury staff mobile phones, iPads, laptops or other media for ease of access and recovery of this information.

### Business Recovery (post decision)
- Once a course of recovery action has been decided upon, business recovery will follow in this order:
  - Activate Recovery Infrastructure:
    - The BCP for systems and communications infrastructure needs to be invoked with inbound calls being diverted and key production systems reverting to the alternate site.
    - For all essential/critical applications, data will be accessed at the alternate site from restored systems or through a data center if applicable.
    - For services provided by third parties such as the central bank, staff may be able to relocate to third party premises to work from designated systems.
  - Survival Level Operations:
    - Initially the business activities at treasury or the alternate site should be limited to core activities.
    - For less time-critical functions, these can be temporarily suspended and/or staff directed to work from home.
  - Escalation:
    - If the incident is severe enough to warrant an extended period away from the primary site (generally exceeding two weeks), business activity may be escalated since a prolonged period at survival level operations could exacerbate the impact of the incident, affect the ability of treasury to maintain essential/critical activities, processes, and systems, and cause undue stress for staff.
    - Where practical, escalation priorities can be predetermined with indicative timeframes noted for the recovery of each business activity or process.
  - Primary Site Recommissioning:
    - Actions to salvage, restore or replace damaged or lost property, facilities and services at the primary site and the process of recommencing business at the primary site.

### Post Incident Review
- Conduct a comprehensive review to ensure the recovery plan and infrastructure are updated or improved based on the experience of the incident.
- Examine each of the six-step processes to identify weaknesses and/or omissions and use the results to revise and update the BCP/DRP.
- Potential outcomes include changes to:
  - business processes
  - underlying infrastructure including systems and facilities at the alternate site
  - enhanced training and testing
  - other changes identified in this phase

### Conclusion
- An ORM framework including a BCP/DRP should be seen as a priority for any treasury given the operational risks that they face and critical functions and activities that they perform.
- The development of a BCP/DRP should not be seen as a one-off project but should become an integral part of the day-to-day operations of treasury.
- The six-step process to develop, implement, test and maintain the BCP/DRP will provide the treasury with the practical steps needed to ensure that this occurs.